Surface: 5000 m2
Project:
• Basic and execution
• Facilities
• Activity
Construction Management
• Installations
• Electricity (Low, Medium Voltage)
• lighting
• Air conditioning
• Fire Protection (PCI)
Medium Voltage:
20,000kVA
Generators:
16,000 kVA
Uninterruptible power supply (UPS):
4,000 kVA
Chillers:
8,000,000 kcal/h